330 kV Leningradskaya NPP-2 HV line. Pulkovskaya substation - Yuzhnaya substation

Program name JSC FGC UES Investment Program for 2015-2019, Russia’s UES development program and scheme for 2015-2021
Coordinator Department of Power Engineering Development in the Ministry of Energy of the Russian Federation
Approval document Decree No. 807 dated October 31. 2014, On Approval of JSC FGC UES Investment Program for 2015-2019|Decree No. 627 of The Ministry of Energy (Russia) dated September 09, 2015
Customers JSC FGC UES
Developers JSC FGC UES
Year of implementation start 2011
Year of implementation ending 2017
Objects of capital construction of engineering and transport infrastructure
Object name 330 kV Leningradskaya NPP-2 HV line. Pulkovskaya substation - Yuzhnaya substation.
Object location the Leningrad Region
Main characteristics of the object 3 units of 330 kV secondary distribution switchgear. 2 shunt reactors x 100 MVAr; 1 shunt reactor x 50 MVAr; 330 kV HV line 90 km. rebuild. of 110 kV HV line 2.4 km; 330 kV cable line 25 km.
Estimated commissioning period 2017
Status of object implementation Engineering completed
Introduction of zones subject to special conditions of territory use Yes